Schedule of Works for Light Rail

Sydney Light Rail Schedule – 1 September 2015 to 30 April 2018

PetersExample:  Anzac Parade, between Dacey Avenue and Todman Avenue 1 December 2016  to   9 November 2017  a total of  343 days

How has major construction been planned and what does it entail?
 The route has been divided into 31 zones, with work staggered to minimise the impact of construction on those who live, work or do business along the route.
 The scheduled major construction timeframe for each zone has been released, so residents and businesses can plan ahead.
 Outside those periods, work will continue on technical fit-out and platform construction, which will be more confined and less intrusive.
 Major construction includes excavation, rebuilding roads and laying tracks.